Hi,
We currently launch our maya render as a group of 4-5 jobs with dependancies. First is a job which updates the database, then the maya render job, then followed by the unlocking of either a db-fail or a db-done job depending on the maya render, and finally, a quicktime generation job.
This was all set up before I started working on pipeline here, and I feel 5 jobs is a bit of visual clutter. What I am trying to do, is to see if I can create a maya job, and add additional work to the agenda, but my question is how the job package affects the agenda/work individual settings.
Is it possible to have the 1-n range work take its cue from the maya job package, while other additional Work has its own 'cmdline' and whatnot?
As I have it laid out at this point, I can create the job with the range, and add my extra database update frames, a quicktime creation frame, and an email frame. I have the dependancies all set up nicely. But these extra work objects in the agenda still take their package from the job, load up like a maya render, and completely ignore my cmdline setting. Is this the expected result and is there any way to have extra frames named/labeled 'dbUpdate', 'quicktime', etc, and run just an arbitrary command?
I am wondering if I would just have to do a completely generic cmdrange job, and explicitly set each work objects command, in order to do this type of set up. Or, maybe I should be doing a maya job, and a second job with the rest of the extra commands.
Thanks!
Justin Israel
Technical Developer
SouthPark Studios